30 November 2011: New Embedded Network

The reconciliation manager wishes to advise participants of a new embedded network to be set up on behalf of Robt. Jones Electricity Network Ltd (RJEN), RFO0011 RJEN EN. As at 9 January 2012, the embedded network will be in place.

New NSP: RFO0011 RJEN EN
Name: 41 Shortland Street, Auckland
Parent NSP: PEN1101 VECT GN
Start Date: 09/01/2012

The embedded network will be reconciled globally.


17 November 2011: New Embedded Network

The reconciliation manager wishes to advise participants of a new embedded network to be set up on behalf of The Embedded Network Company (TENC), TCD0011 TENC EN. As at 20 January 2012, the embedded network will be in place.

New NSP: TCD0011 TENC EN
Name: Chaffers Dock
Parent NSP: CPK0331 CKHK GN
Start Date: 20/01/2012

The embedded network will be reconciled globally.


17 November 2011: New Embedded Network

The reconciliation manager wishes to advise participants of a new embedded network to be set up on behalf of The Embedded Network Company (TENC), TKM0011 TENC EN. As at 20 January 2012, the embedded network will be in place.

New NSP: TKM0011 TENC EN
Name: The Karori Mall
Parent NSP: WIL0331 CKHK GN
Start Date: 20/01/2012

The embedded network will be reconciled globally.


15 November 2011: Temporary POC - TNG0111 LINE GN

The reconciliation manager wishes to advise participants of a change at OKN0111. A temporary POC has been set up to supply load to the region normally supplied at OKN0111 LINE GN. This is for scheduled maintenance at OKN0111 on 27 November 2011.

New (temporary) POC: TNG0111 LINE GN
Flow Direction: X
Balancing Area: OKN0111LINEG
Data supplied on: 27 November 2011
Trading Period 1 - 48

Trading will be reconciled at the temporary NSP TNG0111 LINE GN for the affected day. Please note if maintenance is not able to be done on 27 November 2011 then 4 December 2011 has been identified as the back-up date.


14 November 2011: POSTPONED - EMV0011 EDCL EN

The reconciliation manager wishes to advise participants of a new embedded network to be set up on behalf of EDC Holdings Ltd, EMV0011 EDCL EN has been POSTPONED.

It was set to go live on 1 December 2011, however it has now been delayed indefinetly until notifed otherwise by the newtork owner.

All details will be removed from the NSP mapping table on the registry until further notice.