27 April 2011: Change to the grid - Further MHO0331 (Mangahao)

Therefore a further change to the grid is required at MHO0331 ELEC GN;

Old NSP: MHO0331 ELEC GN
Name: Mangahao
Flow Direction: X
End Date: 30 April 2011 Trading Period: 48

New NSP: MHO0331 ELEC GN
Name: Mangahao
Flow Direction: X,I
Start Date: 1 May 2011 Trading Period: 1

The flow has been updated to include I flow to accommodate the embedded generator


27 April 2011: Change to the grid - MHO0331 (Mangahao)

The reconciliation manager wishes to advise participants of a change to the grid. As at 31 May 2011, the following decommissioning will take place regarding the grid connected generator MHO0331 KING GG :

Old NSP: MHO0331 KING GG
Name: Mangahao
Flow Direction: X,I
End Date: 31 May 2011 Trading Period: 48

The Mangahao generator will become embedded under MHO0331 ELEC GN as at 1 May 2011.


07 April 2011: OKN0111 - TNG0111 Cancelled

The reconciliation manager would like to notify participants that the planned maintenance outage at OKN0111 LINE GN has been cancelled until further notice as notified by the Grid Owner.

The reconciliation manager wishes to advise participants of a change at OKN0111. A temporary POC has been set up to supply load to the region normally supplied at OKN0111 LINE GN. This is for scheduled maintenance at OKN0111 on 3 April 2011.

Decommissioned (temporary) POC: OKN0111 LINE GN
Flow Direction: X
Balancing Area OKN0111LINEG

New (temporary) POC: TNG0111 LINE GN
Flow Direction: X
Balancing Area: OKN0111LINEG
Data supplied on: 03 April 2011
Trading Period 1 - 48

Trading will be reconciled at the temporary NSP TNG0111 LINE GN for the affected day. Please note if maintenance is not able to be done on 3 April 2011 then 10 April 2011 has been identified as the back-up date.


24 March 2011: New Embedded Network - NAH0011 NZAL EN

The reconciliation manager wishes to advise participants of a new embedded network, NAH0011 NZAL EN, operated by New Zealand Airways Ltd. As at 1 May 2011, the embedded network will be in place and reconciled by differencing.

New NSP: NAH0011 NZAL EN
Name: 139 The Terrace Asteron House
Parent NSP: WIL0331 CKHK GN
Start Date: 01/05/2011


21 March 2011: Change to the grid - New POC PEN0251

The reconciliation manager wishes to advise participants of a change to the grid as notified by the Grid Owner. As at 1 May 2011, the following new point of connection (GD) will exist:

NSP: PEN0251 NZRN GD
Flow Direction: X and I
Start Date: 1 May 2011

This is a new 25kV point of supply at Penrose.