What's new?

Subject:

21 October 2009: Updated: Change at SHT0111 LLNW EN

The reconciliation manager wishes to advise participants of a change to an embedded network operated by Lakeland Network. As at 28 October 2009, the following will no longer be in place at SHT0111, Shotover Park. The embedded network will be disconnected and ICPs transferred to FKN0331 LLNW GN:

NSP: SHT0111 LLNW EN
Name: Shotover Park
Parent NSP: FKN0331 DUNE GN
End Date: 28/10/2009

If participants have not already done so, please submit revised trade notifications end dating your buyer or seller contracts currently in place at SHT0111. Furthermore, if you have not done so, please submit a new trade notification for FKN0331 LLNW GN.


20 October 2009: New Embedded Network - Change of Ownership for KCA0011

The reconciliation manager wishes to advise participants of a change of network owner for the following embedded network, KCA0011 (Penrod House). As at 1 November 2009, the embedded network will change from MACQ(Macquarie Goodman) to VDNZ (Viaduct New Zealand Ltd) and the following will be in place;

Old NSP: KCA0011 MACQ EN
Name: Penrod House
Parent NSP: PEN1101 VECT GN
End Date: 31 October 2009

New NSP: KCA0011 VDNZ EN
Name: Penrod House
Parent NSP: PEN1101 VECT GN
Start Date: 1 November 2009

The embedded network will be reconciled globally

Could participants please submit revised trade notifications end dating your buyer or seller contracts currently in place at KCA0011 MACQ and re-issue new notifications for KCA0011 VDNZ.


19 October 2009: Updated - Change to SHT0111

The reconciliation manager has been advised this morning by Powernet that the proposed transition of SHT0111 to FKN0331 LLNW GN did not take place as scheduled due to engineering issues. Therefore SHT0111 is still being feed by the DUNE network. This means the embedded network is still in place

As a result, the reconciliation manager will re-open all participants trade notifications for SHT0111 until the 30 November 2009 and revised notifications published to all trading participants and the system operator. This is due to Powernet not yet knowing when the new planned transition will occur.

The reconciliation manager will ensure all participants are kept up to date in regards to this issue.


15 October 2009: Updated - Change to Start Date for ROM0011 BCRO EN

The reconciliation manager wishes to advise participants of a change to the start date of a new embedded network operated by Body Corporate 169769. As at 1 December 2009, the following will be in place at ROM0011, Royal Oak Mall. The embedded network will be reconciled globally from 1 December 2009:

New NSP: ROM0011 BCRO EN
Name: Royal Oak Mall
Parent NSP: PEN0331 VECT GN
Old Start Date: 01 November 2009
New Start Date: 01 December 2009

The change in start date is in relation to a network agreement not being in place in time for the original start date


09 October 2009: Change to Embedded Network - SHT0111 LLNW EN

The reconciliation manager wishes to advise participants of a change to an embedded network operated by Lakeland Network. As at 18 October 2009, the following will no longer be in place at SHT0111, Shotover Park. The embedded network will be disconnected and ICPs transferred to FKN0331 LLNW GN:

NSP: SHT0111 LLNW EN
Name: Shotover Park
Parent NSP: FKN0331 DUNE GN
End Date: 18/10/2009 (TP 48)

If participants have not already done so, please submit revised trade notifications end dating your buyer or seller contracts currently in place at SHT0111. Furthermore, if you have not done so, please submit a new trade notification for FKN0331 LLNW GN.